Week
Number |
Date |
Task |
Responsibly |
Build Volunteers Needed |
Church Group Volunteering |
Meals |
Daily Devotional |
|
9 |
8/21 |
Continue on the siding , soffits, and trim. Air seal the home. Install the
gutters and downspouts. |
Site Leader Thrivent |
3-4 Crew Leaders 14 Regular Volunteers |
Bethany Lutheran/NKU |
Plan for 28 |
1 or 2 Volunteers |
|
10 |
8/28 |
Prepare to insulate and insulate the walls. Start hanging the drywall on
the ceilings |
Site Leader Thrivent |
3-4 Crew Leaders 14 Reg. Volunteers |
Hebron |
Plan for 28 |
1 or 2 Volunteers |
|
11 |
9/4 |
Complete any remaining work on the exterior and start to hang the
drywall. |
Site Leader |
3-4 Crew Leaders 14 Reg. Volunteers |
OPEN |
Plan for 28 |
1 or 2 Volunteers |
|
12 |
9/11 |
Complete hanging the drywall, install corner bead, and clean the house
out. |
Site Leader Thrivent |
3-4 Crew Leaders 14 Regular Volunteers |
Gloria Dei |
Plan for 28 |
1 or 2 Volunteers |
|
13 |
|
Turn house over to Drywall Finishers |
Subcontractors |
|
--- |
N/A |
N/A |
|
13 |
9/18 |
Building the shed. Work on final grade and seeding the yard. |
Site Leader Thrivent |
3-4 Crew Leaders 14 Reg. Volunteers |
Hebron |
Plan for 28 |
1 or 2 Volunteers |
|
14 |
9/25 |
Clean the interior of the house, wipe down the walls, prime and paint all
the interior walls |
Site Leader Thrivent |
3-4 Crew Leaders 7 Regular Volunteers |
Good Shepherd |
Plan for 15 |
1 or 2 Volunteers |
|
15 |
10/2 |
Install interior doors, casing and baseboard. Paint trim as rooms are
competed. Install underlayment and prep for vinyl flooring. Complete the
shed and paint. |
Site Leader Thrivent |
3-4 Crew Leaders 7 Regular Volunteers |
OPEN |
Plan for 15 |
1 or 2 |
|
16 |
10/9 |
Finish any interior trim install kitchen and bath cabinets. Install hardware
on doors |
Site Leader Thrivent |
3-4 Crew Leaders 7 Reg. Volunteers |
OPEN |
Plan for 15 |
1 or 2 Volunteers |
|
17 |
10/16 |
During week the electric, plumbing and HVAC finish work should be completed
and inspected as needed. |
Subcontractors |
|
--- |
N/A |
N/A |
|
17 |
10/23 |
Install all the shelving and any remaining hardware. Finish touching up the
painting and clean the house, complete landscaping |
Site Leader Thrivent |
3-4 Crew Leaders 7 Regular Volunteers |
OPEN |
Plan for 15 |
1 or 2 Volunteers |
|
18 |
10/30 |
Punch list and prepare for Dedication |
Site Leader Thrivent |
TBD as needed |
--- |
TBD |
|
|
19/20 |
11/6 |
Extra work day if needed |
TBD |
TBD as needed |
|
TBD |
|